US 34 WidenWIDENING EISENHOWER BLVD (US 34)

One of Loveland’s Busiest Roadways is in Need of Important Improvements

Improvements are needed to a 2.5-mile stretch of Eisenhower Boulevard (US 34) between Boise Avenue and Rocky Mountain Avenue to relieve traffic congestion and improve traffic safety.

Turn Lanes, Bike Lanes and Other Improvements are Part of the Proposal

The proposed improvements include:

  • Filling in the areas where a third through lane in each direction is missing
  • Expanding the acceleration/deceleration lanes
  • Adding turn lanes at the Boise intersection
  • Constructing curb, gutter, sidewalk and bike lanes in areas where they are currently missing

This section of Eisenhower (US 34) is just north of the Walmart Super Store, The Greens at Van de Water, Kohl’s, Mountain View High School and Loveland Sports Park.

Estimated Total Cost

 $30,000,000

Resources Available
$5,547,820

Unfunded
$24,452,180